Gauteng transport dept extended bus contract irregularly since 1997 - Public Protector

Close

Embed Video

Gauteng transport dept extended bus contract irregularly since 1997 - Public Protector

Public Protector Busisiwe Mkhwebane
Photo by Reuters
Public Protector Busisiwe Mkhwebane

1st February 2022

By: News24Wire

SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

The Office of the Public Protector has found that the Gauteng Department of Roads and Transport irregularly implemented a provincial transport contract with the Putco bus company.

On Monday, Public Protector Busisiwe Mkhwebane released her findings after several complaints were brought to her office. One of them was a complaint by an organisation called Moloto Corridor Concerned Residents, which said the bus company had been enjoying a monopoly in the industry for the last 20 years.

Advertisement

"We found that the allegation that the GDRT (Gauteng Department of Roads and Transport) irregularly implemented Contract IC52/97 is substantiated. The investigation revealed that the original 136-week contract number IC52/97, which was awarded to Putco on 26 March 1997, had been continuously extended (evergreen contract) as at the date of this report," her office said.

The investigation also revealed that there were 108 bus contracts with similar conditions to the Putco bus contract. The Public Protector's office said the Competition Commission was willing to look into these contracts.

Advertisement

"The conduct of GDRT is in contravention of section 217 of the Constitution, section 38 of the PFMA (Public Finance Management Act), Treasury Regulation 16A6.4, paragraphs 8 and 9 of National Treasury Instruction 3 of 2016/2017 Preventing and Combating Abuse in the Supply Chain Management System, and section 42(3) of the NLTA (National Land Transport Act)," read the report.

The Public Protector called on the Gauteng MEC for Roads and Transport to take note of the final report, adding that the renewal of the contract amounted to "improper conduct and maladministration".

The Public Protector found that the conduct of the GDRT, particularly the [head of department], was improper and constitutes improper conduct as envisaged in the Constitution and maladministration as envisaged in the Public Protector Act.

Mkhwebane has recommended that the head of the department provide her office with quarterly reports of meetings with the national Department of Transport, National Treasury and the Auditor-General to ensure compliance with relevant legislation on procurement processes.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options
Free daily email newsletter Register Now