First phase of Sibanye-Stillwater’s secondary mining thrust given thumbs up


Close

First phase of Sibanye-Stillwater’s secondary mining thrust given thumbs up

Should you have feedback on this article, please complete the fields below.

Please indicate if your feedback is in the form of a letter to the editor that you wish to have published. If so, please be aware that we require that you keep your feedback to below 300 words and we will consider its publication online or in Creamer Media’s print publications, at Creamer Media’s discretion.

We also welcome factual corrections and tip-offs and will protect the identity of our sources, please indicate if this is your wish in your feedback below.


Close

Embed Video

First phase of Sibanye-Stillwater’s secondary mining thrust given thumbs up

Sibanye-Stillwater EVP Lucas Msimanga's presentation covered by Mining Weekly's Martin Creamer. Video: Dalene Creamer.

8th July 2026

By: Martin Creamer
Creamer Media Editor

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

JOHANNESBURG (miningweekly.com) – A lower-risk secondary mining business, which focuses on extracting value from platinum group metals (PGM) surface waste that hosts chrome, is being built by the South Africa PGM Operations of Sibanye-Stillwater.

The opportunity lies in unlocking PGM and chrome value from the large, accessible upper group two (UG2) tailings resources on surface.

Advertisement

UG2 tailings retreatment, fine chrome recovery and processing capability are creating a new value stream.

The first part of the surface processing strategy – Phase 1 of the WLTR recovery plant upgrade project – has already arrived.

Advertisement

This phase, which involves treating tailings to recover chrome as well as PGMs, supports the broader South Africa PGM Operations surface retreatment strategy.

The feasibility study has been completed, board approval has been received, and construction is scheduled to begin in the second half of this year, with commissioning expected by the end of 2027, Sibanye-Stillwater executive VP processing Lucas Msimanga reported during the Capital Day covered by Mining Weekly. (Also watch attached Creamer Media video.)

The projected capital is R0.9-billion, payback is two years, Phase 1’s economic life is six years, net present value is R1-billion, internal rate of return is 43%, and operating costs were described by an upbeat Msimanga as being “very competitive”.

Historical UG2 tailings storage facilities (TSFs) across the Rustenburg and Marikana regions provide the material, the primary value driver is chrome coupled to meaningful PGM upside, and available PGM concentrator capacity offers the capability of recovering PGMs in an integrated and efficient manner.

With a switch to magnetic processing technologies, the surface resources also present a significant chrome recovery opportunity.

A million tons of historic UG2 tailings are there for the taking and Sibanye-Stillwater has vast processing and tailings infrastructure spread across 70 km of PGM footprint to handle current and future mining output.

The Johannesburg Stock Exchange- and New York Stock Exchange-listed mining and marketing company’s vast footprint takes in Marikana as well as the Rustenburg region, and within the footprint are concentrators for primary processing of the material from the underground operations.

Capacity is adequate to process the current and future projects. Total available concentrate capacity across Sibanye-Stillwater’s South Africa PGM operations is 1 605 000 t a month.

All of this is linked to long-term TSFs.  The life of the Paardekraal TSF in Rustenburg extends to 2060, as does the Marikana Pits TSF and Hoedspruit in Marikana extends to 2044.

“We've got the capacity to dispose of those tailings safely, as well as in an environment-friendly manner.

“When processing, we continuously seek to improve recoveries. We’re benchmarking internally as well as externally, and we want to raise recoveries as high as possible,” Msimanga pointed out.

Standout 36% recovery is being achieved by the WTD5, Hoedspruit and Marikana Pits TSFs, with recoveries from the other TSFs ranging from 11% to 17%.

“Our objective is to get close as possible to the 36%, which will be done by optimisation of the TSF operations and the deployment of the right technology,” said Msimanga, who drew attention to the focus of Sibanye-Stillwater’s seven relatively shallow primary adjoining mining projects also being largely on UG2 reef, which, provided the company continues to invest appropriately across concentrators, supports operational reliability.

Targeted sustaining capital has maintained high equipment availability and recovery performance. This approach supports structurally lower unit costs.

The result is a flexible processing platform that supports processing requirements of current operations and positions the business well for future brownfield projects.

Cycle consistent capital investment in processing assets is supporting important availability, which from 2022, has been north of 92%.

A fine chrome magnetic technology introduced is delivering better recoveries.

“Because we're also extracting the chrome, we’re also going to be reducing the tailings volumes, and from a rehabilitation point of view it's got a positive impact up to about 30% and this enhances the overall economics of the operations,” Msimanga reported.

A digital footprint twin has been developed to optimise deposition planning and long-term capacity.

Msimanga described the Marikana Pits TSF as a cornerstone of the surface strategy in that it maximises residue deposition capacity for the WLTR and Kroondal surface concentrators while supporting future underground operations.

“These are existing pits, so it means that, in terms of time to bring those tailings facilities, they can be brought quicker and also at a lesser capital cost.

“We can deal with that in these Marikana Pits TSFs, and they will help us to maximise deposition capacity for the WLTR and Kroondal surface concentrators, while supporting future underground operations.

“So, we've got the resource, we've dealt with the technology, but also, we've got a solution for the tailings disposals, and now this WLTR recovery project to actualise value creation,” said Msimanga.

Transition from Merensky-rich to UG2 tailings is driving a fundamental change in the revenue mix, with chrome becoming a core value driver alongside PGMs.

Surface margins are expected to improve as the portfolio shifts to UG2 and chrome production provides an extra value stream through the PGM price cycle.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE      ARTICLE ENQUIRY      FEEDBACK

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here


About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za