Eskom Green says PFMA approval enables fundraising and partnerships


Close

Eskom Green says PFMA approval enables fundraising and partnerships

Should you have feedback on this article, please complete the fields below.

Please indicate if your feedback is in the form of a letter to the editor that you wish to have published. If so, please be aware that we require that you keep your feedback to below 300 words and we will consider its publication online or in Creamer Media’s print publications, at Creamer Media’s discretion.

We also welcome factual corrections and tip-offs and will protect the identity of our sources, please indicate if this is your wish in your feedback below.


Close

Embed Video

Eskom Green says PFMA approval enables fundraising and partnerships

Eskom renewables group executive Rivoningo Mnisi
Eskom renewables group executive Rivoningo Mnisi

16th July 2026

By: Terence Creamer
Creamer Media Editor

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

Eskom Holdings reports that it has now secured the required approvals to establish Eskom Green as a wholly-owned renewables subsidiary that is able to raise funding and enter into public-private partnerships.

The approvals were made in terms of Section 54(2) of the Public Finance Management Act (PFMA), alongside the applicable conditions of the Eskom Debt Relief Act, which placed restrictions on the raising of new debt for generation investments.

Advertisement

“Eskom Green can now crowd-in external capital and expertise and [the approval] enables private sector investors to be able to partner and invest with Eskom Green and utilise our experience and skills to deliver very compelling and competitive utility-scale renewable energy supply offerings to customers,” Eskom renewables group executive Rivoningo Mnisi said in a statement.

Eskom Green will now initiate a market process to establish a panel of strategic partners to support the delivery of renewable-energy projects through project-financed special purpose vehicles (SPVs) and strategic partnerships.

Advertisement

It has appointed PwC and the Development Bank of Southern Africa to advise it on the process.

The SPV-based funding model would ensure that project-specific debt, liabilities and risks were ring-fenced.

“Eskom Green’s financial exposure to individual projects is therefore limited to its committed equity contributions, with limited recourse to Eskom Holding’s balance sheet or the national fiscus.

“Where government support mechanisms are required to enhance bankability, such support is expected to be targeted, capped and subject to the necessary PFMA and shareholder approvals,” the statement added.

Eskom Green’s mandate included the repowering and repurposing of coal-fired power station sites, and it announced at its launch in June that it was aiming to implement 5.6 GW of renewables by 2030 across 17 projects.

It had a larger goal of implementing 32 GW by 2040 and indicated previously that battery energy storage systems could be integrated into several projects. In addition, it aims to pursue the 1.5 GW Tubatse pumped-storage project in partnership with the private sector.

“The 2025 Integrated Resource Plan states that 102 GW of renewable energy should be delivered by 2042, in line with this, Eskom Green is targeting to deliver up to 32 GW by 2040, which still leaves over two-thirds of the renewable energy generation opportunities open to the private sector,” Eskom Holding CEO Dan Marokane said.

Marokane also described the approvals as an important milestone in the further implementation of Eskom's strategy in the areas of unbundling, delivering utility-scale renewable-energy capacity and reducing carbon emissions and other air pollutants.

Eskom Green also stressed that all its activities would be undertaken in compliance with South Africa’s energy regulatory framework.

This, amid ongoing concern that Eskom Green might not be subjected to the same grid-access rules that independent power producers are facing as they compete for limited grid capacity.

These concerns were raised when Eskom announced in May that construction had started on a 75 MW solar PV project alongside the Lethabo coal-fired power station, in the Free State.

Eskom is funding the R1.2-billion project off its own balance sheet and the Letsatsi JV has been appointed as the engineering, procurement and construction partner.

Mnisi said prevailing grid-access rules had applied and stressed that Eskom Green would receive no preferential treatment from Eskom’s Grid Access Unit.

 

EMAIL THIS ARTICLE      SAVE THIS ARTICLE      ARTICLE ENQUIRY      FEEDBACK

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here


About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za