https://www.polity.org.za
Deepening Democracy through Access to Information
Home / Statements RSS ← Back
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Embed Video

Eskom: Eskom marks one year of no load shedding

Eskom: Eskom marks one year of no load shedding
Photo by Duane

8th August 2016

SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

The content on this page is not written by Polity.org.za, but is supplied by third parties. This content does not constitute news reporting by Polity.org.za.

Tomorrow (09 August 2016) Eskom will mark exactly one year of no load shedding, this is largely due to the rigorous plant maintenance programme that we have executed over the past 12 months.

The adherence to regular scheduled maintenance is managed through the Tetris planning tool which schedule outages based on forecasted demand and maintenance requirements. A key aspect of this includes having a strict winter and summer maintenance budget that comprises 8.5GW for winter and 11.5GW for summer.

In terms of our existing Generation Sustainability Strategy, our aim is to achieve 80% plant availability, 10% planned maintenance and 10% unplanned maintenance over the medium term.

Advertisement

The reduction in unplanned outages contributed to improvements of plant availability and the resultant sharp reduction in the usage of open cycle gas turbines (OCGTs). The last time Eskom ran OCGTs to manage the system was on 14 June 2016.  The OCGT load factor year-to-date is 0.24% versus against a target of 6%. Our target is not to burn any diesel for the rest of the financial year.

The resilience of the power system was stress-tested in April this year following multiple trips of units at three power stations, a move that resulted in a loss of 3 535 MW. No load shedding was implemented due to the increased resilience that Eskom has built into the power system over the past few months.

Advertisement

Moreover, on 1 August 2016 the system experienced the highest peak demand for the year, at 34 922 MW. The demand was met without the need to dispatch Eskom diesel generators. This peak was higher than last year’s peak of 34 481 MW.
Whilst improving the performance of the existing ageing fleet on one hand, Eskom has also managed fast-track the building new generating capacity on the other.

On 27 July 2016 President Jacob Zuma officially launched Unit 4 of the Ingula Pumped Storage Scheme, marking a key milestone towards the full commercial operation of the entire hydroelectric facility ahead of the scheduled deadline of May 2017. Upon completion Ingula will be Africa’s newest and largest pumped storage scheme, and the 19th largest in the world. Ingula’s Unit 4 came into commercial operation on 10 June 2016, six months ahead of schedule. It has been consistently adding 333MW into the national grid to ensure security of supply. It is the first of Ingula’s four units to come into commercial operation. The remaining three units have also been synchronised to the national grid and are on track for commercial operation within the first half of 2017. Once completed, all four units of the Ingula Pumped Storage Scheme will produce a total of 1 332 MW.

Eskom’s capacity expansion programme has so far added 7 364MW of generation capacity, 6 162km of transmission lines and 32 890MVA of substation capacity to the national grid since 2005.

Since inception in 2005, the capacity expansion programme so far added 7 031MW of generation capacity, 6 048km of transmission lines and 31 590 MVA of substation capacity.

Eskom continues to execute its build programme that will bring much-needed power to support South Africa’s economic growth. In February this year Unit 1 of the Kusile power station successfully completed factory acceptance tests, an important milestone towards the synchronisation of the unit. This unit is expected to be commercially operational in July 2018.

Medupi’s Unit 5 completed its factory acceptance tests in December last year, and is expected to come into full commercial operation by March 2018.

The Majuba Rail Project is expected to be completed by December 2017. Once commissioned, the security of coal supply through logistics solutions at both the Majuba and Tutuka power stations will transport approximately 21-million tonnes of coal per year by rail.

The Majuba Rail Project is a component of the Eskom Road to Rail Initiative with the construction of a railway line that links the Majuba Power Station to the main coal railway hub in the town of Ermelo in Mpumalanga. The 68km corridor is the first large greenfield freight-rail infrastructure project to be carried out in South Africa since 1986 and will be operated by Transnet Freight Rail.

Meanwhile, Eskom has successfully completed 5 620 self-funded electrification connections as well as 1 080 farm dweller connections during the course of the 2014/15 financial year. In addition, together with Department of Energy (DoE), Eskom has connected more than 4.6 million households to the national grid since 1991. According to the latest Statistics South Africa report, access to electricity has increased from 35% of households in 1990 to over 90% in 2016. More households will be connected to the grid in an effort to achieve universal access by 2025.

 

Issued by Eskom

EMAIL THIS ARTICLE      SAVE THIS ARTICLE      FEEDBACK

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here


About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za