Charlotte Maxeke: Govt to spend R1bn, repairs expected to be finalised in 2023 - Jack Bloom

Close

Embed Video

Charlotte Maxeke: Govt to spend R1bn, repairs expected to be finalised in 2023 - Jack Bloom

20th May 2022

By: News24Wire

SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

The total cost to repair Charlotte Maxeke Johannesburg Academic Hospital is estimated at R1.1-billion.

The Democratic Alliance's (DA's) Jack Bloom has revealed the final repairs are expected to be completed in December 2023.

Advertisement

Bloom said this information was provided by the provincial department of infrastructure development in the Legislature.

"The lack of parking is currently a major issue at the hospital, but temporary access and parking are scheduled for June to July this year and additional parking from July to October.

Advertisement

"A new dry store will be built by Gift of the Givers from June 2022 to January 2023. A detailed assessment of the fire-damaged areas is due to be completed in June, and the reconstruction work of this area will be done from September 2022 to July 2023."

He said all the blocks and works were supposed to be completed in December next year.

"Although the accident and emergency department was supposed to be opened in April, it is receiving only a limited number of patients as the vandalised CT Scanner is still not fixed," Bloom said.

"This highlights the need for tight security and zero tolerance for corruption to meet deadlines for the hospital to reopen by the end of next year fully," he added.

Bloom warned they would not tolerate further delays.

"Thousands of patients suffer because of the slow progress in fixing this major hospital," he said.

In the report on the hospital's repairs, the Gauteng Department of Infrastructure Development claimed it had taken all reasonable measures to speed up delivery of the project.

"The delays in the approval of the project execution Plan by the Gauteng Health Department have resulted in the project not being implemented timeously. 

"Due to the proclamation signed by the premier (David Makhura), the department (DID) handed the project to the Health Department on 25 February 2022."

According to DID, invoices for all work done to date have to be settled by the department.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options
Free daily email newsletter Register Now