https://www.polity.org.za
Deepening Democracy through Access to Information
Home / News / All News RSS ← Back
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Embed Video

Revised Eskom tariff details to be released on Tuesday

30th November 2009

By: Terence Creamer
Creamer Media Editor

SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

Eskom's "revised submission" to the National Energy Regulator of South Africa (Nersa), which is likely to be substantially lower that the version submitted in September, was delivered on Monday evening, with details to be made public by the State-owned utility on Tuesday.

Nersa told Engineering News Online that it had always anticipated that Eskom, which initially applied for an extension to the September 30, 2009, submission deadline, would submit "additional information" by the end of November.

Advertisement

In fact, Nersa's head of communication and stakeholder management Charles Hlebela said that the timelines for consultation and deliberation on the second multiyear price determination period, or MYPD2, had been designed to accommodate some revisions.

However, should these be "substantial" in nature, Hlebela indicated that Nersa might consider extending the period for public comment, which was also meant to have closed on Monday. But he said that it would be premature to say whether the new submission would definitely alter its already published consultation and approval timelines.

Advertisement

Under Nersa's approved timelines, public hearings were scheduled to take place across all provinces from January 11, 2010, to 22, 2010, with a final decision to be made on February 24.

PROJECT IMPACT

Engineering News Online understands that Eskom has been working on a new scenario, which could reduce the yearly request by ten percentage points, or more, when compared with the original request for increases of 45% a year for the three-year period from April 1, 2010, through to March 31, 2013.

However, it could possibly also highlight the energy-security risks associated with the lower request, which would probably lead to a significant delay in the construction of the R111-billion Kusile power plant, the first unit of which was meant to have come onstream in 2013.

Eskom has confirmed that a hard copy of the revised submission was to be delivered to Nersa by Monday night, but the utility said that it would not comment on the nature of the changes until the details were released at a media conference on Tuesday. The conference would be hosted by acting executive chairperson Mpho Makwana.

Engineering News Online understands that Eskom has been forced to moderate its unpopular application in light of a change of heart within government, which initially supported a relatively swift transition towards cost-reflective tariffs.

Government, it has emerged, has been convinced by arguments suggesting that: such steep increases would have devastating economic impacts; that the future demand trajectory might no longer be as steep post the recession as initially forecast; and that the remaining supply-side gaps should be closed by independent power producers (IPPs).

However, few details have emerged as to what guarantees these potential IPPs would receive to entice them to proceed with their programmes, all of which have been frustrated thus far.

In fact, Eskom, which is still designated as the single buyer of private power, placed its various IPP tender programmes on ice earlier this year, despite having short-listed 23 potential IPP projects, with a combined capacity of 4 500 MW.

The utility claims that it required further clarity from the Department of Energy, which was still drafting an integrated resource plan (IRP), as to how much electricity it should source from IPPs. It also wanted greater regulatory certainty on the cost-recovery mechanism involved.

Engineering News Online understands that Cabinet could be asked to approve the IRP at its next meeting, with an inter-Ministerial committee having met to deliberate on the latest version last week.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE      FEEDBACK

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here


About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za