https://www.polity.org.za
Deepening Democracy through Access to Information
Home / Statements RSS ← Back
Africa|Building|Concrete|Construction|Contractor|Cutting|Engineering|Innovation|PROJECT|Projects|Road|Safety|Sustainable|Training|Infrastructure
Africa|Building|Concrete|Construction|Contractor|Cutting|Engineering|Innovation|PROJECT|Projects|Road|Safety|Sustainable|Training|Infrastructure
africa|building|concrete|construction|contractor|cutting|engineering|innovation|project|projects|road|safety|sustainable|training|infrastructure
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Article Enquiry

MEC Tertuis Simmers on Ashton-Montagu Infrastructure Project

Close

Embed Video

MEC Tertuis Simmers on Ashton-Montagu Infrastructure Project

25th July 2022

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

/ MEDIA STATEMENT / The content on this page is not written by Polity.org.za, but is supplied by third parties. This content does not constitute news reporting by Polity.org.za.

On Saturday 23 July, the Western Cape Minister of Infrastructure, Tertuis Simmers, and Langeberg Mayor, Schalk Van Eeden, officiated the ribbon cutting of the Cogmanskloof Pass in Montagu. This marked the completion of the Western Cape Government’s rehabilitation of 13.4KM of Trunk Road 31/2 from Ashton to Montagu through Cogmanskloof Pass.

Another part of this project – the Ashton Arch bridge - was recently awarded the 2022 Fulton Award for the Best Infrastructure Project and received commendation for Innovation and Invention in Concrete. It is anticipated that more accolades are to follow for the project as it has been entered into the 2022 CESA AON Engineering Excellence Awards, with winners due to be announced on Wednesday 28 September. 

Advertisement

Construction of the pass project commenced in May 2019 and it entailed the reconstruction of the road from the West of Ashton through the Cogmanskloof, onto the East of Montagu. Three bridges - the Ashton bridge, Boy Retief bridge and Voortrekker bridge – were also replaced. A multitude of economic opportunities were unlocked through the project as follows:

  • Over R 79 million spent on emerging contractor development
  • Over 600 individual work opportunities created
  • Over R 600 000 spent on training courses for local labourers
  • Over R 16.5 million spent on local subcontractors, manufacturers, and suppliers

At the completion of the project a total of 42% of the contract value was allocated to the creation of economic opportunities and entrepreneurial capacity in the surrounding areas. 

Advertisement

Minister Simmers said: “The opening of the Cogmanskloof Pass is not only a historic moment for the Western Cape Government,  it is an even greater one for the community of this region. Nearly 630 job opportunities were created during the various construction phases of this project, and we certainly expect more opportunities to be created as result of the rehabilitation of this infrastructure. The R62 is a major thoroughfare between the N1 and N2, and this project improves the current road into a dual carriageway allowing unrestricted movement towards Swellendam to the N2, as well as major tourist routes (R60 towards Oudtshoorn).  We look forward to receiving an influx of tourists and commerce through this gateway.”

Additional work conducted at Cogmanskloof included:

  • reconstruction of the roadway;
  • the addition of 1.5m wide surfaced shoulders;
  • raising the existing road level at various positions to improve flood protection;
  • reconstruction of the bridge at km 22.2 (Boy Retief Bridge);
  • improving the horizontal alignment between km 23.7 and km 24.2 (Aasvoëlkrans);
  • construction of scour protection at the existing bridge at km 23.59 (Billy Loftus Bridge); and,
  • construction of rest areas and pedestrian walkways.

The primary objective of this project was to reconstruct the roadway to a higher standard to improve traffic and pedestrian safety, as well as improve flood capacity of bridges and prevent overtopping of the road during floods.

A special feature of the project is the Ashton Arch, which is South Africa’s first concrete tied arch bridge constructed using a transverse launching method. It represents a proud monument for the Western Cape Government, the people of the Ashton-Montagu area, and all the contractors, team members and suppliers who were involved in the project.

“The Western Cape Government continues to pave the way in providing cutting edge infrastructure projects, which are both sustainable and innovative. We are building the Western Cape, and building our economy,” concluded Simmers.

 

Issued by Western Cape Infrastructure

EMAIL THIS ARTICLE      SAVE THIS ARTICLE ARTICLE ENQUIRY

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

 

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options
Free daily email newsletter Register Now