107.5 MW temporary Moz power plant up and running in 14 weeks

18th July 2012

By: Terence Creamer
Creamer Media Editor

SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

A 107.5 MW temporary gas-fired power plant was officially inaugurated on Wednesday by Mozambique President Armando Emilio Guebuza, at a ceremony held at Gigawatt Park, in Ressano Garcia, a town on the border with South Africa.

International temporary power specialist Aggreko developed the project, which would operate until July 2014, in joint venture with South Africa’s Shanduka Group.

Advertisement

The power, produced using gas from Sasol’s Temane gas fields, would be sold to Electricidade de Moçambique (EDM) and Eskom. EDM would consume 15 MW and Eskom the 92.5 MW balance and both EDM CE Augusto Sousa and Eskom CE Brian Dames attended the inauguration of the facility.

The cross-border venture was constructed and commissioned on a fast-tracked 14-week delivery schedule, using containerised power generation units, shipped in from Aggreko’s Dumbarton, Scotland, facilities.

Advertisement

The joint venture also built a 1.2 km high-pressure gas pipeline, gas processing and depressurising infrastructure, a major substation and 1.5 km of 275 kV transmission line.

The accelerated deployment was necessary given that Sasol would reallocate the gas to other ventures after July 2014.

Shanduka Group executive chairperson Cyril Ramaphosa said the power, while temporary, would help meet the immediate needs of South Africa and Mozambique, and provided a model for public-private partnerships and cross-border collaboration.

Aggreko CE Rupert Soames said he hoped the project would be a “pathfinder for other countries seeking to make the most of their resources to optimise the supply of power across the region”.

Soames indicated that the London-listed group was offering similar “bridging” capacity in other parts the world and that he saw potential for a number of other projects across Africa.
 

EMAIL THIS ARTICLE      SAVE THIS ARTICLE      FEEDBACK

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here


About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za