Inquiry hears Transnet paid R42.5bn for new locomotives

Close

Embed Video

Inquiry hears Transnet paid R42.5bn for new locomotives

 Inquiry hears Transnet paid R42.5bn for new locomotives

10th July 2019

By: News24Wire

SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

Transnet has to date spent R42.5-billion on acquiring 1 259 new locomotives meant to upgrade its ageing fleet, some R3.9-billion more than it originally budgeted for, the commission of inquiry into State capture has heard.  

The commission has been investigating allegations of State capture, corruption and fraud since August 2018.

Advertisement

The commission, chaired by Justice Raymond Zondo, on Wednesday received five files containing detailed invoices for Transnet's multi billion-rand series of tenders for the new engines. The three related tenders, for 95, 100 and 1064 new engines, have been dogged by allegations of kickbacks, irregularities and ballooning prices.

The commission started hearing evidence about the locomotive tenders in early May, 2019. This was put on hold for the commission to focus on corruption and kickbacks in the airline industry, as well as the Waterkloof landing, between June 13 and July 9. 

Advertisement

On Wednesday the commission heard evidence from Helen Walsh, the acting general manager for governance, risk and compliance in the State-run freight rail's company's finance department.

Walsh gave evidence on Transnet's payments to the four original equipment manufacturers for the 1259 locomotives – General Electric, Bombardier Transport, China South Rail and China North Rail. She also provided details on relocation costs, and advisory fees paid to global consultancy McKinsey and Gupta-linked company Regiments.

She said that, to date, Transnet had paid R42 501 186 193.59.

She could not say how much Transnet still has to pay. 

Ballooning costs 

The inquiry has previously heard that the initial estimated cost for the project was R38.6-billion. The State-owned freight rail's acting CEO, Mohammed Mahomedy, in late May said cost escalations were not justifiable.

Walsh told the commission that Regiments had been paid a total of R305-million (including VAT) in advisory fees between 2014 and 2016. McKinsey, meanwhile, had been paid R11-million. 

Jonathan Bloom, of MNS Attorneys, previously told the commission that Transnet's treasury was more than capable of facilitating loans for the payments and that an advisory firm like Regiments was not needed.

"One wonders why this particular situation was allowed to occur," he said.

The inquiry has adjourned for the day and will resume tomorrow.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options
Free daily email newsletter Register Now