ActionSA President to Unveil Plan to End Loadshedding Following Oversight Visit by Mpumalanga Premier Candidate

Close

Embed Video

ActionSA President to Unveil Plan to End Loadshedding Following Oversight Visit by Mpumalanga Premier Candidate

ActionSA President to Unveil Plan to End Loadshedding Following Oversight Visit by Mpumalanga Premier Candidate

16th February 2024

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

/ MEDIA STATEMENT / The content on this page is not written by Polity.org.za, but is supplied by third parties. This content does not constitute news reporting by Polity.org.za.

ActionSA conducted an oversight visit to the Kusile Power Station yesterday, Thursday, 15 February 2024. The visit confirmed what we have always known about Kusile Power Station which has been plagued by technical problems, defects and corruption over the years.

As such, ActionSA President, Herman Mashaba, will, next week Thursday 22 February 2024, unveil ActionSA’s plan to bring an end to loadshedding.

Advertisement

During the visit, we discovered that since 17 September 2022, Kusile Power station experienced a fire in the gas air heater of Unit 5 during a commissioning exercise. To date, the cause of the fire is still unknown. This is deeply concerning as his seems to be a recurring problem. A few years ago, the power station experienced a similar incident in Unit 2 which resulted in a further12-month delay of completion of the plant. 

In addition to this, the SOE sited technical issues and major plant defects, which have the potential to significantly reduce the Energy availability in multiple units, as reasons for the delay of the completion of the plant to date.

Advertisement

The five major plant defects at Kusile include the following:

·Kusile Pulse Jet Fabric Filter Plant (PJFF) poor performance due to inadequate pulsing system and flue gas flow entry;

·Kusile Gas Air Heater (GAH) mechanical performance, erosion, and operational performance in terms of ash carryover and outlet temperature stratification;

·Kusile Furnace Exit Gas Temperature resulting in excessive Reheater Spray Water flow;

·Kusile Milling plant defects; and

·Kusile Air and Flue Gas ducting erosion.

In the midst of the increasingly ubiquitous bouts of loadshedding, which already have a devastating impact on the economy and day to day lives of South Africans, it was disappointing to learn that the SOE only envisages getting Unit 5 online by December 2024 which regrettably means more loadshedding in the months to come.

As ActionSA, we urge the Special Investigating Unit (SIU) that is investigating instances of corruption and conflicts of interest related to the Medupi and Kusile, with 29 contracts valued at R135 billion under review, to expedite the process which we hope will lead to prosecutions. It should be considered treason for this SOE under the ANC-led government to continue to arrest the growth and development of South Africa. 

An ActionSA government will turn the tide and secure our energy future and propel South Africa into a new age of prosperity and economic growth.

 

 

Issued by ActionSA Mpumalanga Premier Candidate Thoko Mashiane                                                   

EMAIL THIS ARTICLE      SAVE THIS ARTICLE ARTICLE ENQUIRY

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

 

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options
Free daily email newsletter Register Now