When is an adjudicator’s decision unenforceable?

25th October 2021

When is an adjudicator’s decision unenforceable?

Adjudication is a dispute resolution process created by contract in many modern standard form construction contracts.

A common feature of adjudication clauses is that an adjudicator’s decision is binding on the parties, albeit not final, unless neither party gives a notice of dissatisfaction in relation to the decision within a stipulated time limit.

Adjudication was born out of the necessity in a construction contract setting to have a means of resolving disputes speedily without the expeditious execution of the contract being unduly retarded.

Where a losing party fails or refuses to comply with an adjudicator’s decision, the successful party’s remedy is to apply to court for a court order directing compliance on the part of the loser.

There is a long line of cases in our jurisprudence in which adjudicators’ decisions have been enforced despite all manner of ingenious arguments raised by the losing party as to why the adjudicator’s decision should not be enforced.

In the nature of adjudication, it is a means of dispensing fairly rough‑and‑ready justice within what can be considered tight timeframes compared to the timeframes in normal dispute resolution processes.

It is therefore accepted that, whether or not an adjudicator gets it wrong with reference to the facts or the applicable law, his decision is binding and enforceable more so as it is open to the loser to take the dispute forward for final determination usually by arbitration or by the decision of a court.

This also means that an adjudicator’s decision is not amenable to being reviewed and set aside by a court. There has been more than one recent unsuccessful attempt by a losing party to have a court set an adjudicator’s decision aside on review.

A review in this sense is not an appeal but an attack on the procedural propriety of the process. In one case the loser complained that the principles of natural justice had not been observed because it had not been given an adequate opportunity to present its case although the specific procedural steps provided for in the adjudication clause had been properly observed.

First of all the court held that the principles of natural justice do not apply in adjudication and secondly that any review of an adjudication decision was inappropriate vis-à-vis the losing party’s right and entitlement to have the adjudicator’s decision set aside in arbitration proceedings.

JURISDICTION

One of the very few grounds for avoiding compliance with an adjudicator’s decision arises if the adjudicator has rendered a decision which manifestly falls outside of the scope of what he has been called upon to decide.

This very question arose in a recent case in the Johannesburg High Court.

The relevant facts in the Framatome case were that:

COURT’S DECISION

Eskom argued that the adjudicator had given a decision in respect of a dispute which had not been referred to him and as such his decision, holding that the Contractor’s quotation was deemed to be accepted, was a nullity and without any legal force or effect. The Contractor argued that to adopt such a standpoint in relation to adjudications would undermine the rationale of adjudication.

Although Eskom’s argument in this regard was based on the principles applicable in arbitrations, it also referred to English cases dealing with jurisdictional challenges in relation to adjudicators’ decisions.

The sense of the English cases is that:

The court adopted the view that South African law ought to follow English law in relation to the question of an adjudicator’s jurisdiction. The judge said that adjudicators’ decisions should be enforced as binding on the parties unless a respectable case or a clear case has been made out that the adjudicator exceeded his jurisdiction. If it is not clear, the parties must be held bound by the decision in the interim.

On the facts the judge concluded that the question which had been referred to the adjudicator for decision was whether the Project Manager’s assessment was correct and not the question as to whether the Project Manager had assessed the compensation event timeously where the failure to do so might bring the deeming provisions in the Contract into play.

As such, the court concluded that the adjudicator had answered the wrong question which fell outside the scope of his jurisdiction and as such his decision that the Contractor’s quotation was binding was invalid and unenforceable.

CONCLUSION

Parties must take care to articulate the dispute which is to be referred for adjudication as broadly as is reasonably feasible to avoid problems down the line in relation to enforcing the adjudicator’s decision.

Having said that, what emerges from the case is that a loser trying to avoid an adjudicator’s decision will have to make out a clear and strong case to the effect that the adjudicator has strayed beyond what he was called upon to decide.

Written by Alastair Hay, Cox Yeats Attorneys