Eskom says ‘unexpected challenges’ during Koeberg Unit 1 outage will delay restart

22nd March 2023 By: Terence Creamer - Creamer Media Editor

Eskom says ‘unexpected challenges’ during Koeberg Unit 1 outage will delay restart

Unit 1 steam generator being moved to the storage building
Photo by: Eskom

The first Unit 1 steam generator at the Koeberg power station has been removed from the containment building and placed into an on-site storage building – a development that Eskom describes as a major milestone for a project that has had numerous false starts during previous outages.

However, the State-owned utility has also confirmed that, as a result of “unexpected challenges” during the current long-duration outage, the original return to service date of early June is “no longer achievable”.

However, Electricity Minister Dr Kgosientsho Ramokgopa later revealed that the project was running 45 days behind schedule, which meant the unit was now unlikely to be available to support South Africa through the high-demand winter period.

“Although every effort is being made to reduce the impact, we are currently running a few weeks late,” Eskom said in a statement, adding that the generation production plan was being updated to minimise the impact of the projected delay.

The removal of the first steam generator came only days after the National Nuclear Regulator (NNR) announced that the 60-day period for receiving written representations from members of the public on Koeberg’s application to operate beyond its mid-2024 licence expiry date had closed.

While central to the utility’s plan to extend the life of the nuclear power station for a further 20 years, the replacement project has faced heavy criticism from both environmental groups and energy commentators.

Environmental opponents to the extension have already raised concerns about the consultation process being pursued by the NNR and have also expressed anxiety about the safety case for the life-extension, as well as with the project’s rising costs and corruption at Eskom.

Questions are also continually being raised about the direct and indirect costs of the project, with Eskom having acknowledged that the 2010 cost estimate of R20-billion is no longer accurate but has not yet provided a revised expenditure figure.

The indirect costs, meanwhile, have also been calculated to be substantial, given ongoing loadshedding and the fact that having a Koeberg unit out of service for most of 2023 will add one stage to loadshedding when such cuts are implemented.

Once the Unit 1 replacement is completed, Eskom intends pursuing a similar long-duration outage at Unit 2, leaving Eskom without electricity production from half of Koeberg for most of 2023.

The Unit 1 outage began on December 10 and was expected to continue for about 180 days, while Unit 2 will be shut in September for a similar period after a previous attempt to replace the steam generators was postponed when it emerged that Eskom’s storage facilities had not been completed in time.

Eskom insists, however, that the new steam generators are the last large component replacements needed to ensure Koeberg can operate safely for the requested additional 20-year period.

It also underlines the engineering and logistical complexity of the removal of the first steam generators, explaining that it involved moving steam generators that are installed vertically and taking them out of the containment building horizontally at an elevation of 20 m before placing them on a flatbed transporter.

The old steam generators are painted in a white coating as a preventative measure to eliminate the chance of spreading any surface contamination, before being placed in the storage facility that will be sealed with a concrete door. Eskom then has ten years to dispose of the steam generators.

In a statement Eskom noted that each steam generator is 22 m long, or the height of a six-story building, and weighs over 320 t, which the utility notes as being heavier than a Boeing 747.

Eskom also indicates that the removal and replacement of Unit 1’s other two steam generators will involve the following sequence of activities:

“After which we still need to complete the maintenance activities scheduled for the outage, commission all the systems, refuel the reactor, and return the unit to service,” the utility said in a statement.