Electricity Regulation Act (4/2006): Medium Term Risk Mitigation Project IPP Procurement Programme 2012 (G 36005, Notice 1076)

19th December 2012 By: Asha Ramsaran

The Minister of Energy ("the Minister''), in consultation with the National Energy Regulator of South Africa ("NERSA"), acting under section 34(1) of the Electricity Regulation ·Act 4 of 2006 (as amended) (the "ERA") and the Electricity Regulations on New Generation Capacity (published as GNR. 399 in Government Gazette No. 34262 dated 04 May 2011) ("Regulations"), has determined as follows: