SPECIAL REPORT OF THE AUDITOR-GENERAL
INVESTIGATION INTO THE MPUMALANGA RURAL HOUSING PROJECT
(SOUTH AFRICAN HOUSING FUND):
Contents
1: Introduction
2: Mandate and method of reporting
3: Nature and extent of the audit
4: Audit findings
5: Conclusions
6: Recommendations
7: Appreciation
1. Introduction
1.1 On 24 April 1997 the former Director-General of the National
Department of Housing informed the Auditor-General of certain alleged irregularities
concerning the approval of a subsidy-linked project for the development
of affordable housing in the Mpumalanga Province, granted to an entity
styled Motheo Construction (Pty) Ltd. This was one of the biggest contracts
in low-cost housing awarded by the government, and it was for 10 500 houses
at a total cost of R190 890 000.
1.2 On 6 May 1997 he requested the Auditor-General to audit the approval
process followed in granting a subsidy-linked project to Motheo Construction
(Pty) Ltd. This request was agreed to.
1.3 The purpose of this audit was to establish whether there was:
-
proper approval for the project at national and provincial levels;
-
any misrepresentation;
-
a proper agreement between the Provincial Housing Board and Motheo
Construction (Pty) Ltd;
-
compliance with the relevant Acts and regulations.
1.4 As a result of, inter alia, extensive press reporting on the
above project and the materiality of the amounts involved, it was decided
to deal with the findings of the audit in a separate Report.
1.5 The purpose of this Report is to convey the findings of the audit
so that timely corrective steps could be taken where necessary.
2. Mandate and method of reporting
2.1 The content of this Report is based on the requirements of section
188(1) of the Constitution of the Republic of South Africa, 1996 (Act No.108
of 1996) and sections 3 and 5 of the Auditor-General Act, 1995 (Act No.12
of 1995). In compiling the Report, where possible the emphasis was placed
on the more material aspects.
2.2 Owing to- the fact that there are two Accounting Officers involved
in the Housing Subsidy scheme - one at national level and the other at
provincial level it is envisaged that this Report will be tabled both in
Parliament and in the Mpumalanga Legislature. I am of the opinion that
it should first be dealt with at provincial level.
3. Nature and extent of the audit
3.1 The findings of this Report are based on information gained from
files, from reviewing documentation submitted to this Office as
well as from a variety of other sources and interviews. Where possible
the validity of information was verified. Where parties were not compelled
by the Auditor-General Act, 1995 (Act No.12 of 1995) to supply information,
but indicated their willingness to assist this Office, such information
was obtained and analysed.
3.2 Owing to the nature of some of the aspects involved, for instance
the fact that parties outside the Government are involved in this project,
it was not always possible to obtain all the information and documentation
required. Because of the inherent limitations of any audit, this Report
does not purport to have identified all the shortcomings and/or irregularities
that may possibly have occurred.
4. Audit findings
The key findings set out below are based on a detailed report that was
forwarded on 17 July 1997 to the Acting Director-General of Housing, the
Director-General of the Mpumalanga Province and the Head of the Department
of Local Government, Housing and Land Administration in the Mpumalanga
Province, who is the Accounting Officer for housing subsidies in the Province.
The above parties' comments were received on 23 July 1997 and 14 August
1997 and are taken into account in this Report, where it is deemed appropriate.
The key findings of the audit are briefly as follows:
4.1 General
4.1.1 Proper approval for the rural housing project was not obtained.
Although the Mpumalanga Housing Board took a decision in this regard, this
decision is considered to be invalid as there was no quorum at the particular
meeting, the information needed to make a proper decision was largely lacking
and no funds were available to finance this project. In fact, the funds
for housing projects were already overcommitted to a considerable extent.
4.1.2 Conclusive evidence that any misrepresentations took place could
not be found. There is, however, a reasonable possibility that misrepresentation
concerning the assumed involvement of a financial institution did occur.
4.1.3 Whereas there is a written agreement between the Mpumalanga Housing
Board and Motheo Construction (Pty) Ltd. it was not necessarily signed
with the proper authority of the Board nor did it comply with the terms
and conditions usually applicable to the housing subsidy scheme.
4.1.4 There was almost complete disregard for the due process and proper
procedure in terms of the requirements of the National Department of Housing's
implementation manual. For example, the proposed project was for the largest
part not assessed in accordance with the fifteen evaluation criteria contained
in that manual.
4.2 Approval of the Motheo Construction (Pty) Ltd project by the
Mpumalanga Provincial Housing Board
4.2.1 As the main board, the Mpumalanga Provincial Housing Board has
an Executive Committee to assist it. All the proposed projects are initially
reviewed by the Executive Committee, which makes preliminary decisions
on such projects, "hereafter such projects are submitted to the main board
for one of three decisions, being:
-
Confirmation of the decision of the Executive Committee;
-
Rejection of a project; or
-
Approval of a project in principle.
4.2.2 Significant reservations are expressed as to whether the Executive
Committee had in fact had sufficient information on 16 January 1997 to
take any resolution regarding the awarding of the Mpumalanga Rural Housing
project to Motheo Construction (Pty) Ltd. These reservations are based
on the following:
-
No exact details of the proposed project were disclosed.
-
The role of the financial institution that was supposedly part of
this project was not defined.
-
No information about Motheo Construction (Pty) Ltd and it capabilities
was disclosed.
-
Site information was sketchy and clarity was apparently not obtained on
the ability of the selected sites to carry development.
-
No proposal was placed before the Executive Committee.
-
No indication of any financial implications was given.
-
It is not clear whether the Provincial Housing Board made its decision
based on an evaluation of the size of the top structure, the delivery programme
and the support of the local community as was indicated to the Portfolio
Committee on Housing of Parliament on 3 June 1997 by the former Chairman
of the Board, as no indication could be found that information relating
hereto had been presented to the Executive Committee.
4.2.3 The minutes of the 18th main board meeting of the Mpumalanga Provincial
Housing Board, held on 30 January 1997, state, inter alla, the following:
"4. Ratification of the 18th Executive Committee meeting The Board
ratified the Minutes of the 18th Executive Committee meeting."
4.2.4 Only six members of the Mpumalanga Provincial Housing Board are indicated
as having been present at the above meeting. The minutes of this Board
meeting correspond to the attendance register for this meeting as regards
the number and identity of the Board members present, except that another
Board member was also present at this meeting according to the attendance
register.
According to the contents of the minutes of the 18th Board Meeting of
the Mpumalanga Provincial Housing Board, it is clear that the approval
of the rural housing project is deficient. The reasons for this are the
following:
-
In ratifying the Minutes of the 1 8th Executive Committee Meeting,
it is not clear whether the Board in fact approved the proposal of Motheo
Construction (Pty) Ltd. This Office was, however, advised that the proposal
had in fact been approved, even though the minutes are not clear on the
facts.
-
The Minutes of the 18th Board Meeting do not disclose whether the Board
in fact applied its mind to the proposal concerned.
-
Most significant, however, is the fact that - according to the minutes
- the membership of the Board consists of eleven people, six of whom are
indicated as having been present, two of whom are indicated as having been
absent and three of whom are indicated as having extended their apologies.
It was established that seven Board members had in fact been present
at the meeting concerned. In documentation relating to the identity of
the Board members, it was noted that the Board had originally had sixteen
members, "hereafter it had been reduced to twelve with effect from 1 February
1997. Section 11 (7) read with Section 7(3) of the Housing Arrangements
Act, 1993 (Act No. 155 of 1993) states that the quorum of the meeting of
the Provincial Housing Board shall be two thirds of its members. There
was thus not a quorum at this particular Board Meeting. Consequently, any
decision taken at this meeting would have been ultra vires as no
proper Board was constituted at the meeting.
-
There were no funds available for this project, since the Department
of Local Government, Housing and Land Administration in Mpumalanga had
already overcommitted itself to fund projects to the amount of R313 467
230 as at 29 April 1997.
At the commencement of the 1997/1998 financial year, the Department
had funds totalling R158 181 665 available for housing projects. As at
29 April 1997, the cash flow information provided to the National Director-General
of Housing indicated that the Department's commitments for the 1997/1998
financial year amounted to R471 648 895.
This estimate includes an amount of R143 451 963 relating to rural
housing initiatives. It is thus evident that the Department had totally
overcommitted itself, even without the addition of further rural housing
initiatives.
The funds available at the commencement of the 1997/1998 financial
year, being R158 181 665, do not include the national allocation to the
Mpumalanga Province for the 1997/1998 financial year. This amount was,
however, still unknown at that stage.
4.2.6 The former Director-General of the National Department of Housing
had advised the Head of the Department of Local Government, Housing and
Land Administration to seek possible funding in inactive projects. However,
effecting a reallocation of funds from inactive projects entails the cancellation
of unproductive contracts between the latter Department and the relevant
developers. To terminate these contracts, agreement to such effect has
to be reached between the latter Department and the relevant developers.
According to the Department of Local Government, Housing and Land Administration
in the Mpumalanga Province, the effect of this action would realise only
R132 439 350 if all the contracts that could be cancelled were indeed cancelled.
4.2.7 The following observations on the above position can therefore
be made:
-
Cancellations of unproductive contracts would not necessarily have
a positive effect on the cash flow of the Department of Local Government,
Housing and Land Administration because of its significant over commitment
on available funding;
-
It is evident that the cancellations were not a certainty when the
contract was signed, and the Department of Local Government, Housing and
Land Administration committed itself to the expenditure concerned;
-
The budget allocation to Mpumalanga for the 1997/1998 financial year
was also uncertain when the contract was signed.
4.2.8 The Departments seriously overcommitted financial position-thus creates
a serious risk of the Department of Local Government, Housing and Land
Administration not being able to meet its commitments if and when they
become due.
4.3 The proposal of Motheo Construction (Pty) Ltd
4.3.1 The above proposal appears to have been published, at least in
draft form, late in 1996, although officials of the Department of Local
Government, Housing and Land Administration informed this Office that it
was first presented at the briefing meeting held on 24 February 1 997.
4.3.2 A significant feature of this proposal is that it refers to a
joint venture between Motheo Construction (Pty) Ltd and a financial institution
as regards the provision of rural housing. It is further evident from reading
this proposal that the intention expressed is that Motheo Construction
(Pty) Ltd was to enter into a development undertaking with the assistance
of a financial institution.
4.3.3 The proposal also provides for a number of requirements to be
met in order to comply with a fast delivery schedule. These requirements
included the following:
-
"All subsidies of R17 250 and provision made for this amount to be
increased in accordance with the inflation rate";
-
"Bulk and connector infrastructure grant funding for enviroloo".
4.3.4 As regards these requirements, the following observations are made:
-
The government subsidy scheme for housing does not provide for a
subsidy of R17 250 per se as the maximum subsidy available is R15
000. Furthermore, the subsidy scheme does not make provision for inflation.
-
It is not clear why bulk and connector infrastructure grant funding
would be required for the installation of an enviroloo, since such installation
would entail that no services in the sense of sewerage lines et cetera
would have to be provided. The cost of installing an enviroloo could
therefore have been funded by a saving on the cost of such services. Bulk
and connector infrastructure grant funding would then also have been unnecessary.
4.4 Evaluation of the Motheo proposal by the Mpumalanga Provincial
Housing Board
4.4.1 The National Department of Housing's implementation manual sets
out a number of requirements which an application for a project linked
subsidy must meet before the Provincial Housing Board can approve it. However,
no formal documentation constituting an application by Motheo Construction
(Pty) Ltd could be found. The following are the more material procedures
that have not been adhered to:
-
The developer is required to satisfy a Provincial Housing Board that it
has sufficient access to financial resources and managerial competence
in order to undertake the proposed projects successfully.
No evidence could be found that any financial information relating
to Motheo Construction (Pty) Ltd had been placed before the Provincial
Housing Board. The fact that Motheo Construction (Pty) Ltd maintained in
its proposal that it was in a joint venture with a financial institution
created the possibility that if the Provincial Housing Board had applied
its mind, it could have reached the conclusion that Motheo Construction
(Pty) Ltd would be financed by the financial institution.
It is quite possible that such an understanding could have existed
within the Department of Local Government, Housing and Land Administration.
-
If a development is undertaken as a joint venture, the legal competence,
financial position and technical expertise of the parties to the joint
venture as a whole should be assessed by the Provincial Housing Board in
order to ascertain whether the developers concerned are financially, technically
and managerially capable of handling the proposed project successfully.
Motheo Construction (Pty) Ltd clearly insisted that it was involved
in a joint venture operation with a financial institution. However, no
copy of an agreement specifically entered into between Motheo Construction
(Pty) Ltd and the financial institution to substantiate the representation
that the proposal was a joint venture between a financial institution and
Motheo Construction (Pty) Ltd could be found.
The Provincial Housing Board appears not to have been concerned about
this specific requirement and as such it did not assess the legal competence
and financial position of this joint venture. The decision-makers in the
Province indicated that they were satisfied that it was not necessary to
determine the legal competence and financial position of Motheo Construction
(Pty) Ltd. since a financial institution was involved in the joint venture.
This understanding appears to have resulted from the knowledge of the
Provincial Housing Board and the Department of Local Government,
Housing and Land Administration of the underlying memorandum of understanding
between the Mpumalanga Province and the financial institution concerned.
It is, however, clear that in this instance neither the Provincial Housing
Board nor the Department had specifically assessed the legal competence
of the ostensible joint venture between a financial institution and Motheo
Construction (Pty) Ltd. Furthermore, it can be mentioned that the financial
institution concerned denies being involved in the proposed project.
-
Any application submitted for approval by the Provincial Housing
Board in subsidy-linked projects has to be accompanied by, inter alla,
the following:
-
In the case of an application being made for an increase in the amount
of the subsidy in order to compensate the for costs incurred
as a result of abnormal geotechnical and locational factors, the amount
of the increase for which application is made should be indicated, and
that application should be motivated fully. In the present instance, it
was noted that Motheo Construction (Pty) Ltd had effectively applied for
a subsidy in excess of the maximum subsidy allowed. No detailed motivation
for such an increase in the subsidy was provided in the proposal.
-
A copy of the social compact agreement between the community-based partner
of the developer and other stakeholders in the project has to be submitted.
No copies of social compact agreements between Motheo Construction (Pty)
Ltd and any community based partners were submitted.
The Head of the Department of Local Government, Housing and Land Administration
explained to Audit that the concept of social compact agreements is outdated
and not in use, especially in view of the emphasis on delivery.
-
If a copy of the agreement between the developer and any particular stakeholder
has not been obtained at the time of submission of the proposal, a summary
of the steps taken to obtain the stakeholder's approval and the motivation
for nevertheless undertaking the project has to be supplied. No summary
of the proposed steps detailed in the Motheo proposal regarding the involvement
of a financial institution and how it would be procured was submitted.
-
A locality sketch, a preliminary lay-out plan and proposed house
plans or sketches with full specifications for top structures should accompany
the proposal. A perusal of the proposal submitted by Motheo Construction
(Pty) Ltd indicates that none of the aforementioned items accompanied the
said proposal. Nor were these items available to the Provincial Housing
Board when it ostensibly made a decision on the Motheo project. The version
of Motheo's proposal provided to this Office on 10 June 1997 does, however,
contain such information. This appears to have been made available to the
Head of the Department of Local Government, Housing and Land Administration
on 24 February 1997.
-
The proposal has to be accompanied by details of quality control
measures that have to be adopted and details of warranties in respect of
building defects. No evidence of such details could be found in the proposal
forwarded by Motheo Construction (Pty) Ltd. The Department of Local Government,
Housing and Land Administration usually also insists on retentions and
professional indemnities. There were, however, no retentions provided for
in the subsidy agreement nor in the Certificates of Progress Payments.
-
A list of names of all the professional consultants and contractors
that will be utilised to plan, design and execute the project has to be
supplied. No such information was supplied in the proposal of Motheo Construction
(Pty) Ltd.
-
A programme for the implementation of the project has to be supplied.
The proposal submitted by Motheo Construction (Pty) Ltd contains no programme
for the implementation of the project. The proposal subsequently handed
to this Office by representatives of Motheo Construction (Pty) Ltd contains
only a theoretical time schedule.
-
According to the Manual, applications will be accepted upon submission
within a programme of publicly-specified dates. Projects submitted by such
closing dates will then be evaluated on a comparative basis. However, no
such actions took place and it is thus evident that the Motheo proposal
was considered in a manner contrary to the aforementioned prescriptions
of the Manual.
-
The Manual prescribes that no projects will be approved unless funds
are allocated to the project. However, it is evident from the above that
on the one hand no funds were allocated for the purposes of this project
as at the date of its ostensible approval by the Mpumalanga Provincial
Housing Board, being 30 January 1997 and on the other hand the Mpumalanga
Provincial Housing Board did not apply its mind as to whether there were
funds allocated to the project or not.
-
The Manual requires that the Secretariat of the Provincial Housing Board
has to assess an application in accordance with the evaluation criteria
contained in the Manual. Such criteria include the following:
-
The degree to which all relevant stakeholders are included in the social
compact agreement underlying the project proposal, and the significance
and possible impact on the project of the exclusion of any stakeholders
from it. This does not appear to have been considered.
-
The extent to which the project satisfies the housing needs of an
identified and defined target market and the relative urgency of such needs.
No evidence that this was considered could be submitted.
-
The extent to which the project contributes to the gainful employment
of community members through the use of local small building contractors
and labour intensive building methods. This aspect was apparently addressed
only in a superficial manner.
-
The extent to which minimum norms and standards regarding health
and safety are met and are acceptable to the client community. This aspect
was apparently only addressed in a superficial manner.
-
The extent to which innovative and well-considered planning and design
contribute to a wholesome living environment that will instil pride and
a sense of belonging among residents. This aspect was not dealt with when
the Mpumalanga Provincial Housing Board considered the application.
-
The extent to which the targeted market and community will be able
to afford the costs of residential property, ongoing maintenance and related
services and facilities. No evidence was provided to indicate that this
aspect had been considered.
-
The extent to which the project is integrated and compatible with
surrounding development in a manner that impacts positively on natural
and built-up surroundings. No evidence was provided to indicate that this
aspect had been considered.
-
The extent to which construction methods employed in the project
are effective, viable and practical in relation to the physical, climatological,
geo-technical and topographical characteristics of the project site. There
appeared to be no evidence that this aspect had been considered.
-
The extent to which methods employed are replicable, thereby contributing
to a comprehensive, sustainable housing delivery process. There appeared
to be no evidence that this aspect had been considered.
-
The level of accountability and gearing of public resources. Although the
Motheo proposal attempts to address this requirement, no evidence was presented
that it had been considered properly.
-
The capacity of the relevant local authority to deliver and perform
effectively and productively. No evidence was found that this aspect had
been considered.
-
The contribution that approaches adopted in the project will make
towards optimising the longer term social and economic benefits of the
project to the target community. This aspect appears to have been considered,
albeit in a superficial manner.
-
The extent to which the project affords the beneficiary a choice
in satisfying the housing needs. No evidence could be found that this aspect
had been considered.
-
The extent to which stakeholders support the project and the extent to
which they have agreed to co-operate in its implementation. No evidence
could be found that this aspect had been considered.
-
Value for money to be received by beneficiaries in terms of the pricing
of the products to be offered. No evidence could be found that this aspect
had been considered.
-
Subsequent to its assessment of a project, according to the criteria
referred to above, the Secretariat, if satisfied, has to prepare a motivated
recommendation to a Provincial Housing Board for consideration. No evidence
of such a motivation having been provided to the Mpumalanga Provincial
Housing Board could be found.
4.5 The Agreement relating to the subsidisation of project-based
housing developments
4.5.1 The Agreement with Motheo was signed on 14 March 1997. With regard
to the Agreement and the signing of the Agreement, the following audit
observations are made:
-
The Mpumalanga Provincial Housing Board did not authorise the Chairman
to enter into the Agreement. It is, however, possible that there might
have been a general mandate to that effect.
-
There were no funds in place when the Agreement was signed.
-
There were still various problems with the contents of the Agreement on
the date on which it was signed.
-
Notwithstanding the fact that the Agreement refers to a financial institution
as well as a draft agreement to be signed with a financial institution,
there was no such draft agreement and yet the parties signed the
Agreement.
-
The contract was signed for a subsidy of R15 000 each for 10 500
houses plus an additional 15% geo-technical allowance and a R930 bulk and
connector infrastructure grant for all 10 500 houses. This could not have
been done since each individual erf had to be evaluated in order
to qualify for an additional subsidy to the maximum of 15% of the original
amount of the subsidy. Thee bulk and connector infrastructure grant of
R930 was evidently not to be derived from subsidisation by the National
Housing Hoard but from a different source, and should therefore not have
been included in this particular contract.
4.5.2 The inclusion of the bulk and connector infrastructure grant of R930
per erf in the Subsidisation Agreement implies an inflation of R9 765 000
of the subsidy agreed to by the Department of Local Government, Housing
and Land Administration as well as the Mpumalanga Provincial Housing Board.
Neither the Department nor the Mpumalanga Provincial Housing Board could,
however, commit funds for the South African Housing Fund for this purpose,
as bulk and connector infrastructure grants are derived from a different
source.
4.5.3 The Manual dictates that progress draws can be made in the following
manner:
-
1 st draw: Engineering design
-
2nd draw: Town planning and land survey charges
-
3rd draw: Total serviced site costs
-
4th draw: On registration of transfer of any particular erf an amount equal
to the difference between the infrastructure cost of that erf and the amount
already paid in terms of the first three draws.
-
5th draw: Upon completion of the top structure, the balance of the subsidy
will be paid to the Developer.
In this regard it was noted that the 4th progress draw indicated in the
Manual is not contained in the Agreement, as the latter requires the 4th
draw to be made upon completion of the top structure. The Agreement also
requires the final infrastructure cost to be paid on hand-over of the improved
site. It is further evident that the agreed details for progress payments,
excluding payment of the bulk and connector infrastructure grant, constitutes
a subsidy payment of R17 250 per erf. The implication of this is
that the subsidy agreed to by the Mpumalanga Provincial Housing Board and
the Department of Local Government, Housing and Land Administration is
inflated by R23 625 000 in respect of the 10 500 houses to be built in
terms of the Agreement.
4.5.4 It has further been noted that in terms of Clause 3.8.5 of the
Agreement, the 5th draw for final infrastructure costs on hand-over of
the improved site will be paid on the basis of 50% of an amount of R2 325
on completion of each individual top structure and 50% of the amount of
R2 325 on the completion of transfer to the beneficiaries of each completed
top structure, but not later than 30 days after the top structure has been
handed over to the local authority concerned. The effect of this is the
following:
-
The Department of Local Government, Housing and Land Administration agreed
to pay an effective subsidy of R17 250 per site. The total amount payable
in terms of this, excluding the bulk and connector infrastructure grant,
amounts to R181 125 000. Given the structure of the 5th draw, this would
translate into an amount of R24 412 500 being advanced by the Department
as an interest-free loan facility of R24 412 500 to Motheo Construction
(Pty) Ltd. This is contrary to well established principles of government
funding, which provide that no payment be effected until value has been
received and furthermore that no loans be granted by the government to
private individuals without proper and specific authorisation thereto,
and pursuant to an agreement being reached upon any interest payable.
-
In the event of the contract being construed as providing only for
a subsidy of R1 000 per unit, the specific structure regarding the 5th
draw still provides for a loan advance of up to R24 412 500.
4.5.5 The terms of the Agreement were amended by a letter, dated 14 March
1997, signed by the Head of the Department of Local Government, Housing
and Land Administration addressed to Motheo Construction (Pty) Ltd. It
is, inter aria, indicated in this letter that the geo-technical
allowance could not be set at 15% of R1 000 per erf, but at an amount up
to 15%, and that the Department is not convinced as to why Motheo Construction
(Pty) Ltd needed an extra R930 for each enviroloo owing to the saving effected
on infrastructure such as sewerage. Furthermore, this letter reads as follows:
"The contract has been signed subject to an amicable resolution of
the points raised in paragraphs 1 and 2 of this letter. This letter should
thus be regarded as an Addendum to the Contract herein enclosed".
4.5.6 There are significant reservations as to whether this letter in fact
constitutes an addendum to the Agreement. These reservations are based
on Clause 8 of the Agreement, which reads as follows:
"This Agreement, (including the Appendices hereto) correctly reflects
the intentions of the parties and constitutes the entire Agreement between
the parties. No variation of, or addition to, or cancellation of this Agreement
and no notation of this Agreement and no waiver by any one party of any
of its rights hereof shall be of any force or effect unless reduced
to writing and signed by the parties hereto or their duly authorised agents;
provided that the Board shall be entitled, by means of notice to the Developer
to amend, vary or substitute the subsidy procedures in ways not inconsistent
with the eventual receipt by beneficiaries of the benefit of individual
subsidies and not inconsistent with the Developer receiving payments as
specified in Clause 3."
It appears that the above letter constitutes a notice in line with the
provisions of Clause 8 of the Agreement. However, since this letter deals
with issues relevant to the eventual receipt by beneficiaries of benefits
of individual subsidies as well as matters relating to Clause 3 of the
Agreement, it is insufficient to amend the conditions by mere notice to
the Developer and it should have been effected in writing under signature
of all the parties concerned.
4.6 Miscellaneous findings
4.6.1 It appears that three houses had to be demolished in Hazyview
owing to a dispute regarding the relevant area, since the relevant tribal
authority had not been consulted about the development of such area in
Hazyview.
4.6.2 The first payment of R9 240 000 had already been made to Motheo
Construction (Pty) Ltd. notwithstanding the fact that no application for
the change of land use in Hazyview, Tongaat and Badplaas had been received
as at 6 June 1997 for the Nelspruit area by the Local Authority concerned.
4.6.3 There are two accounting officers involved in the delivery of
housing by means of the Housing Subsidy Scheme, the one being the accounting
officer of the South African Housing Fund. The other accounting officer
is in a Province for which money is made available to him/her in terms
of section 13(1) of the Housing Arrangements Act, 1993 (Act No. 155 of
1993) for the performance of the functions of a Provincial Housing Board,
which include the payment of subsidies.
This situation creates some difficulty, especially since the funds for
the housing subsidies are not provided on the vote of a Province, but are
made available to a Province from the South African Housing Fund for the
payment of subsidies. Furthermore, only one official in a Province, who
does not necessarily have to be the Director general of the Province, is
made accountable for these funds. There are thus two levels of accountability
and the question arises as to what extent the accounting officer of the
South African Housing Fund is accountable for the housing fund money spent
by the accounting officer in a Province.
One way to resolve this problem would be to make the funds for housing
subsidies available directly on the relevant vote of the Province.
4.6.4 Section 11 (3)(b) of the Housing Arrangements Act, 1993, determines
that one third of the members of a Provincial Housing Board should be nominated
from the sectors or subsectors supplying and financing housing goods and
services in the provinces. This stipulation in the Act may have the effect
that the appointment of certain members of the Board may result in a conflict
of interests. This appears to have been the case with the Mpumalanga Housing
Board.
5. Conclusions
5.1 It is evident from the findings in paragraph 4 of the report that
important rules and regulations were not adhered to by the Mpumalanga Provincial
Housing Board as well as the Department of Local Government, Housing and
Land Administration in the Mpumalanga Province.
5.2 Furthermore, it is possible that the members of the Mpumalanga Housing
Board as well as officials of the Department of Local Government, Housing
and Land Administration had been influenced by the possibility of a financial
institution being involved, because they were under the impression that
financial institutions had been involved in similar projects in the past.
5.3 The contents of this Report clearly indicate substantial disregard
for the due process and proper procedure by individuals in positions of
public trust. It is evident that the interests of the taxpayer and the
principles of good governance have not been served in this instance. The
contrived nature of the agreement is clearly evident, but the reasons and
full implications thereof are not.
6. Recommendations
6.1 The National Department of Housing indicated that the subject of
possible misrepresentation by certain individuals would be discussed with
the Public Protector for possible action by him.
6.2 This Office is, however, of the opinion that the most appropriate
manner to address all the uncertainties that still exist is to appoint
a Commission of Enquiry to establish, inter alla, the following:
-
Whether any misrepresentation was made by any individual or organisation
to the Provincial Housing Board or the Department of Local Government,
Housing and Land Administration or any other party to this project.
-
Whether there were, in view of the allegations that were made in
the public media, any family or other close relationships involved in the
awarding of this project to Motheo Construction (Pty) Ltd.
-
What the reasons and full implications of the contrived nature of
the agreement with Motheo Construction (Pty) Ltd were.
7. Appreciation
I should like to express my appreciation of the courtesy extended, and
assistance rendered, by the staff of the various entities visited during
the audit.
Pretoria, 28/08/1997
H.E. KLUEVER
Auditor-General.