https://www.polity.org.za
Deepening Democracy through Access to Information
Home / Opinion / Real Economy RSS ← Back
Africa|Building|Coal|Construction|Cutting|Energy|Power|Projects|Solar|Storage|System|Maintenance
Africa|Building|Coal|Construction|Cutting|Energy|Power|Projects|Solar|Storage|System|Maintenance
africa|building|coal|construction|cutting|energy|power|projects|solar|storage|system|maintenance
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Article Enquiry

Cut procurement coat to grid cloth

Close

Embed Video

Cut procurement coat to grid cloth

Photo of Terence Creamer

10th June 2022

By: Terence Creamer
Creamer Media Editor

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

As Eskom moves to draft a comprehensive plan for ending the protracted electricity crisis, a series of interesting proposals are emerging on ways to end load-shedding over the coming two years.

Most commentators agree that there is an urgent need to accelerate the introduction of new electricity generation and storage capacity as Eskom’s overutilised and undermaintained coal fleet effectively decommissions itself.

Advertisement

Given their time-to-deploy, cost and funding advantages, new electricity will have to arise over the period in the form of wind and solar photovoltaic installations, both rooftop and utility scale, with battery energy storage adding system flexibility.

There is also emerging consensus that relying on the long- promised recovery in the coal fleet’s energy availability factor (EAF) would be reckless, as it would hinge on a dramatic reversal in a trend that has been in place for several years at a time when enormous monetary, system space and skills impediments remain.

Advertisement

It would probably be more useful to declare several units to be officially decommissioned, so that maintenance priority can be given to those newer or larger units with the highest stabilising impact.

From that smaller and more realistic base, the coal fleet’s EAF will normalise to within international-type benchmarks, the true supply-demand gap will be plain to see, alongside the one that will arise with further decommissioning.

With the role of coal in ending load-shedding settled, attention can then be given to accelerating the introduction of new energy and capacity by easing any and all impediments to such a roll-out by independent power producers, municipalities, companies, individuals and Eskom, particularly where its repowering investments are aligned with the just energy transition.

There may be some debate as to whether emergency powers are required to stimulate such an acceleration and there is even more debate about which entity is best placed to oversee such a response.

There is far less debate, however, on the importance of grid access to this process.

Here, Eskom and its Generation Connection Capacity Assessment (GCCA) should be deployed more deliberately to guide the procurement of large-scale projects and to direct the siting of distributed generation assets.

One relatively simple way to do so would be to use the GCCA to inject a spatial dimension into the procurement of new electricity – and to do so purposely, rather than by default as is currently the case as transmission constraints emerge in key renewables regions.

This is not to say that significant grid investment is not necessary; it most certainly is. However, building it out into the Cape provinces will take time that South Africa simply does not have on its side.

By cutting our procurement coat to our current grid cloth, bidders would have vastly improved grid-connection visibility and certainty, Eskom would be able to ramp up the provision of budget quotes and the construction of new generation and storage assets can proceed at a speed and scale commensurate with the crisis.

 

EMAIL THIS ARTICLE      SAVE THIS ARTICLE ARTICLE ENQUIRY

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za