https://www.polity.org.za
Deepening Democracy through Access to Information
Home / News / All News RSS ← Back
Africa|Energy|Eskom|Power|System
Africa|Energy|Eskom|Power|System
africa|energy|eskom|power|system
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Article Enquiry

Stage 16 loadshedding code seeks to reduce human error not signal imminent surge in cuts – Nersa

Close

Embed Video

Stage 16 loadshedding code seeks to reduce human error not signal imminent surge in cuts – Nersa

NRS Association management committee chairperson Vally Padayachee explains the reason for the new loadshedding standard at a Nersa briefing. Recorded & Editing by Shadwyn Dikinson. 16.4.2024

16th April 2024

By: Terence Creamer
Creamer Media Editor

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

The National Energy Regulator of South Africa (Nersa) has belatedly moved to quell concern that its recent approval of a new loadshedding code of practice, which increases the number of potential stages from eight to 16, represents a signal that the prospect for higher levels of loadshedding is imminent.

Following extensive public consultations undertaken by the National Rationalised Specifications (NRS) Association of South Africa, the third edition of the NRS048-9 standard was approved by the regulator for use by Eskom and municipal system operators during times of electricity constraint.

Advertisement

It increases the number of loadshedding stages from the eight outlined in the second edition to 16 with the aim of preventing the system from succumbing to a blackout; a scenario from which it could take South Africa weeks to recover.

At Stage 16, which Nersa fulltime regulator for electricity Nhlanhla Gumede described as a “highly unlikely scenario”, 80% of demand would go unmet, and South African households and businesses would experience 32 hours of power cuts over a 32-hour period.

Advertisement

At Stage 8, a level not yet implemented by Eskom, 40% of the load would be shed, equating to 16 hours over 32 hours.

The utility has already implemented loadshedding at Stage 6 on several occasions, which under the third edition of NRS048-9, involves 30% of the load not being met, or 12 hours of loadshedding over 32 hours.

In a media briefing hosted partly to explain the code and partly to allay fears, Gumede stressed that the approval of the new code was “not  an indication that greater levels of loadshedding are imminent”.

NRS Association management committee chairperson Vally Padayachee said the updated standard had been developed using a scenario-planning methodology across the entire country load so as to address critical uncertainties, “including the unlikely event of Stage 16”.

“In so doing, we significantly mitigated the propensity of human error,” he added.

Prior to the approval of the update to NRS048-9, Eskom and municipal system operators had no firm guidance regarding the implementation of loadshedding beyond Stage 8, which was left open to their discretion.

Padayachee argued that the lack of clear guidelines beyond Stage 8 posed a risk, particularly given that system operators would be making difficult decisions in an emergency situation where stress levels would be heightened, which could in turn increase the propensity for error.

The new code of practice, he added, would help prepare operators to protect the national electricity grid, as it outlined a structured and proactive approach to addressing a crisis should one arise.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE ARTICLE ENQUIRY

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options
Free daily email newsletter Register Now