https://www.polity.org.za
Deepening Democracy through Access to Information
Home / Opinion / Latest Opinions RSS ← Back
Coal|Energy|Eskom|Flow|Gas|Gas-to-power|Power|Resources|System|Flow|Maintenance|Solutions
Coal|Energy|Eskom|Flow|Gas|Gas-to-power|Power|Resources|System|Flow|Maintenance|Solutions
coal|energy|eskom|flow-company|gas|gas-to-power|power|resources|system|flow-industry-term|maintenance|solutions
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Article Enquiry

Time to act

Close

Embed Video

Time to act

Time to act

17th January 2020

By: Terence Creamer
Creamer Media Editor

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

The return of load-shedding, together with what is a truly dire prognosis for system stability, should surely have been the wake-up call government required to finally begin implementing its very own Integrated Resource Plan 2019 (IRP 2019).

Instead, the only indication that the Department of Mineral Resources and Energy (DMRE) is even slightly alive to the crisis is the issuance of a Request for Information (RFI) for emergency supply solutions.

Advertisement

The RFI in itself is not a problem, as the IRP 2019 does include an open-ended allocation for the period 2019 to 2022 that will be determined by “the extent of the short-term capacity and energy gap”.

The immediate gap is estimated in the document to be between 2 000 MW and 3 000 MW, but could increase to 5 000 MW should Eskom decide, later this month, to pursue a new maintenance philosophy that increases the number of units out for planned outage so as to address the steep rise in unplanned breakdowns.

Advertisement

The problem with the RFI is that it is being pursued in isolation from the rest of the IRP 2019 and is potentially distracting from and delaying the implementation of sensible, low-cost and least-regret solutions.

Despite including some expensive policy adjustments, such as imported hydro, Eskom batteries and forced-in private coal, the IRP 2019 still offers a rational roadmap forward. Therefore, if the DMRE were truly serious about tackling the crisis, it would be moving to implement it.

Practically, that would mean not only the Risk Mitigation Power Procurement Programme, which should flow from the RFI responses, but also the immediate release of bid documents for the next round of renewable- energy procurement, as well as the gas-to-power programme.

Likewise, the department could announce an immediate moratorium, at least until 2022, on the regulatory constraints still blocking some 2 000 MW of capacity that private enterprises and households are willing to build and finance.

What is no longer acceptable is for the department to look primarily towards Eskom and the Department of Public Enterprises for a way out of this predicament. If it continues to do so, the crisis will endure for far longer than would otherwise be the case, with devastating consequences for the economy.

Terence Creamer | Editor

EMAIL THIS ARTICLE      SAVE THIS ARTICLE ARTICLE ENQUIRY

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options
Free daily email newsletter Register Now