https://www.polity.org.za
Deepening Democracy through Access to Information
Home / Legal Briefs / SchoemanLaw Inc RSS ← Back
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Embed Video

Resolving Construction and Contractor Disputes

Resolving Construction and Contractor Disputes

13th July 2016

SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

Building disputes happen fairly often, and in a large portion of cases end up before an arbitrator or worse, in court. The main reason behind this seems to be two-fold. 

Firstly, due to the fact that most construction work involve various unforeseen events, with the result that the contract and time-frame of the building project needs to be altered, and the alterations or variations(as the term is used in the industry) is not always recorded in writing. Secondly, the ambiguity of the contract used, which does not clearly set out the procedures for the variation of the agreement and when to record a dispute or refer it to arbitration.

Advertisement

In a 2013 decision by the Supreme Court of Appeal (“SCA”), the court dismissed an order by the Eastern Cape High Court in Grahamstown, which in essence, held that an arbitrator’s appointment was premature.

Background of the Dispute
The parties entered into a JBCC Principal Building Contract 2004 (4 ed). An arbitrator was appointed when disagreements arose regarding the employer’s liability for various claims lodged by the contractor. Prior to the practical completion of the project, the contractor submitted various extension of time claims in terms of the agreement. In the majority of the claims the principal agent either; failed to make a decision, or rejected the claims by the contractor. The contractor subsequently failed to give the necessary notice to challenge the principal agent’s decisions in terms of the agreement, in relation to the disputed claims which had been referred to the principal agent. According to the employer, there was thus no arbitral dispute between the parties because the principal agent’s decision was final. 

Advertisement

The applicant (the employer in this case), based on the above argument, objected to the arbitrator’s appointment on the following two grounds:

  1. the dispute arose before practical completion of the works; and
  2. the respondent (the contractor) was purporting to revive claims that had been finally disposed of by the principal agent during the course of construction.

The High Court agreed with the employer, and held that in respect of the claims where the contractor has not complied with the agreement, it has forfeited those claims. It ordered that there were thus no “arbitral dispute”.

Decision by the SCA
The employer, further to the above, also alleged that, even if a dispute came into existence, it was not competent to submit it to arbitration due to the dispute arising prior to the practical completion of the project, and that it was thus required to be resolved by adjudication. The SCA dismissed this objection by the employer on the grounds that the manner of resolving the dispute depends on whether it was submitted for resolution before or after practical completion of the project, not on when it arose. If a party wanted a dispute resolved before practical completion, adjudication was the way to go. The contractor thus has the option to complete the work and then submit the dispute to arbitration.

It was held that whether the contractor’s claims had merit or not, was no reason why the arbitrator should not have jurisdiction to consider them. If the claims did not have merit, then it only meant that the employer might have a good defence, and the arbitrator may dismiss the claims.

The decisions made by the principal agent under the JBCC in relation to the initial claims that were refused in the course of construction, became final and binding and no dispute capable of being submitted to arbitration came into existence in relation to those claims. But those are not the claims that was the issue before the court. The contractor alleged an entitlement to submit revised claims to the principal agent, which it did when it submitted its ‘consolidated claim’. Those are the claims that became disputed once the principal agent failed to respond to the contractor’s request for a decision.
A dispute thereupon arose as to the validity of those claims, which was one “arising out of or concerning the agreement” – it is only because the agreement exists that the dispute has arisen – that is subject to resolution by arbitration.

Conclusion
The above example indicates that the disputes arising from a building agreement during a project may be very technical and difficult to resolve, even if the process is followed according to the relevant agreement used. It is therefore wise and, in most circumstances, more cost efficient to have a qualified professional go through the intended contract prior to either party signing the document.  Also obtain legal advice during the construction phase, especially in circumstances where there are numerous claims, extensions and alteration or variation orders involved.

Written by André Nortjé, Junior Associate, SchoemanLaw

EMAIL THIS ARTICLE      SAVE THIS ARTICLE

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options
Free daily email newsletter Register Now