Nersa unveils adjudication schedule for Eskom’s 15% hike application

Close

Embed Video

Nersa unveils adjudication schedule for Eskom’s 15% hike application

Nersa unveils adjudication schedule for Eskom’s 15% hike application
Photo by Creamer Media

23rd October 2018

By: Terence Creamer
Creamer Media Editor

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

The National Energy Regulator of South African (Nersa) has unveiled its adjudication timetable for Eskom’s fourth multiyear price determination (MYPD4) revenue application, which will include public hearings in all nine provinces between January 14 and February 1, 2019.

The regulator has also confirmed that it will deal with Eskom’s regulatory clearing account (RCA) submission for the 2017/18 financial year – the final year of the MYPD3 tariff period – as part of the same adjudication process.

Advertisement

The State-owned utility has applied for allowable revenue of R219-billion for 2019/20, R252-billion for 2020/21 and R291-billion for 2021/22.

If granted, it would equate to tariff hikes of 15% a year over the three years, before any RCA allowances.

Advertisement

Nersa has already confirmed that Eskom is allowed to recover R32.7-billion, over a four-year period, approved as part of three separate RCA applications adjudicated earlier this year. The decision will translate to Eskom’s 2019/20 tariff rising by 4.41% in addition to any MYPD4-related hikes approved.

Nersa reported that an analysis of the MYPD4 and RCA applications had shown them to be in compliance with both the minimum information requirements for tariff applications, as well as the MYPD methodology.

It had, therefore, decided to follow “due regulatory processes” in assessing the applications, starting with the publication of the two applications on its website on October 19 and a call for written comments from stakeholders.

The closing date for written submissions is November 30, with public hearings scheduled to begin in Cape Town on January 14 and conclude in Gauteng on January 31 and February 1.

Nersa will make a determination on both applications on March 1, 2019.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE ARTICLE ENQUIRY

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options
Free daily email newsletter Register Now